KW Eemshaven emerging
Thursday, July 15, 2010
The Eemshaven area is looking like an ant-hill
these days. Two major power plant construction projects have been
started to secure future power supply for the Netherlands. At the
new built RWE KW Eemshaven, Wagenborg Nedlift is playing a major
role in the project management, co-ordination and execution of the
logistic activities of the steel construction. This initially
covers 7,000 tons of steel construction, with all kinds of weights
and dimensions. Wagenborg Nedlift’s scope is to transport the parts
from quayside up to storage area at the plant. Last week, some
extraordinary parts were transported. Two large steel structures of
128 tons each, 28 meters long and 6,1 meters wide were offloaded
from inland water vessels onto trailer by two heavy mobile cranes.
During the night, the convoy slowly moved to the RWE site, thus
avoiding any obstruction in normal working routine for the
construction crew at site. With same cranes used for the
transhipment operation, the parts were offloaded at site. They are
now waiting for installation at their final destination in the
boiler building at 102 (!) meter height. In total, 28,000 tons of
steel construction parts will be used for the new powerplant.
Back to the overview