Transport and lifting Moerdijk
Monday, September 06, 2010
Transport and lifting
works at Moerdijk
At the site of Essent’s new powerplant
in Moerdijk, Wagenborg Nedlift has been quite active with heavy
equipment lately. First of all, the boiler modules of the new
boiler unit were installed. With weights up to 243 ton per unit,
Wagenborg Nedlift provided a 750 tons and a 350 tons crawler to do
the job. Together with the Spanish construction company of the
power plant, these lifting works were carried out completely
according to schedule. In the meanwhile, a heavy transformer sailed
from Korea to Moerdijk. It was a challenge to get this giant of 278
tons onto foundation. Wagenborg Nedlift’s hydraulic lifting gantry
was perfect fit for the job and within hours, the transformer was
put in place.



Back to the overview