Shutdown BP Lingen
Shutdown 2006 - carrying out all transport and lifting works
during the 3 week shutdown in September 2006, including shutdown
management, co-ordination, and engineering. Wagenborg Nedlift
carried out the vertical and horizontal transport for the 4 main
contractors and various subcontractors with an average of 40 cranes
on site.