Rig Move by Foxdrill and Nedlift
Tuesday, September 22, 2009
Recently the crew of Wagenborg
Nedlift and Wagenborg Foxdrill have
completed a masterpiece. In less than three weeks a complete rig
move was carried out, with the rig being handed over ready to
operate to a German drilling contractor.

Such a high level logistical operation drew considerable
attention in the industry, as Wagenborg Nedlift’s project manager,
Gert Kleis explains: “The onshore rig T46 had been stored for a
while at our premises in Schoonebeek. In early June this year we
received an order from a client to move the rig to its new drilling
spot in Brihuega, which is roughly 80 kilometres northeast of
Madrid. The deadline to have the rig fully operational at its new
base was around a month later in early July.”
The move represented a considerable challenge for Wagenborg
Nedlift, together with its sister companies, Wagenborg Foxdrill and
Wagenborg Spain. The first task involved drawing up a project plan
and arranging the necessary transport permits. In terms of the
transportation, the rig consists of approximately 100 truck loads,
with half of them being normal loads, and the other being more
difficult, exceptional or heavy loads.
As Gert explains, to reach the site in Spain, Wagenborg Nedlift had
to arrange the transport permits with the relevant local
authorities in Belgium, France and Spain. “With our experience in
heavy transport in those countries, we were able to arrange all the
necessary paperwork very quickly,” he says. “However, for the
really heavy cargo, such as a mud pump that weighed 58 tonnes and
was 8.35 meters long, road transportation was no option. Permit
procedures would delay the project by two months so to avoid this,
another mode of transport was chosen; the ferry from Zeebrugge to
Bilbao. About 20 transport combinations loaded with the heaviest
pieces were shipped using this method.”
At the Brihuega site, the Wagenborg Foxdrill crew, led by
Foxdrill’s project manager Roger Vleeshouwers, had prepared
everything needed to receive the trucks and commence the assembly
of the rig. This was carried out in close co-operation with
Wagenborg’s branch office in Madrid, which took care of hiring all
of the necessary local resources. “At this stage in the work it is
very important to have 100 per cent perfect communication between
the different parts of the operation,” says Gert. “It is vital that
trailers carrying foundation pieces and substructure components
arrive at the site first. This way the trucks can be offloaded
quickly and rig pieces can be placed onto the foundations directly
without intermediate storage. It is a significant benefit that all
activities involved in this operation are in Wagenborg hands. The
close co-operation on transport and assembly work leads to a smooth
operation, avoiding having to wait hours for our trucks and
personnel. Importantly our customer benefits from this the most -
the rig move was even completed before the actual contract
deadline. Ultimately, Wagenborg likes to cherish its customers. For
example, Wagenborg Nedlift Spain arranged housing, cars and other
related facilities for the project manager and crew of the German
client involved in the operation.”
')";>')";>
T46
The T46 rig is an onshore oil and gas rig, able to drill
approximately six kilometres. The rig will be operating in Spain
for approximately three years on various drilling locations
This artcle was published on
europeanoilandgas.co.uk
Back to the overview